Why keep documentation of what is happening to Thurston?

The Thurston Neighborhood will be unreversably altered by the new school construction. For many neighbors and parents, excitement for a new school for the kindergarten and elementary school children first changed to disbelieve when being confronted with the new plan from the board of education. Finally frustration and anger set in, when it became clear that the promise of cooperation between AAPS and communities would not be honored.

In March 2024, the board of education (BOE) of the Ann Arbor Public Schools (AAPS), the fourth largest school district in Michigan, had to admit to a $25 Million deficit in their budget due to a clerical error. This was the first sign that the board is unfit to lead the district in projects of high magnitude. By now, it has also become clear that they are not open about the $1 Billion bond voted on by taxpayers in 2019. Since plans have finally been published, public outcry at board meetings became so frequent and strong that board members curbed public engagement and time for community members to speak.

The bond proposal citizens voted on is not honored by the board members, instead more and more problems managing the school construction projects are coming to light all over town. In the Thurston neighborhood, the impact the new construction plans have on students/parents/teachers, the environment, the neighborhood and the City of Ann Arbor are numerous.

Here are a few general points:

  • There was no public bidding process to award the $1 Billion construction contract. Instead, residents found out that Gilbane Construction (headquartered in Rhode Island) had been named general managers of the whole project with an office at the AAPS administration building and unfettered power of all aspects of the planning and construction process. The total Investment will be nearly $1.5 Billion Dollars including the one existing and two possible future sinking funds (see slide 12).

  • Until April 2025, the bond committee only consisted of Susan Baskett and Susan Schmidt, chair and vice-chair of the BOE.

  • A Bond Advisory Group was announced in early 2022 but by January 2026, still has never met.

  • There is no running budget from Gilbane to APPS, tax payers have no idea if money is used properly and wisely. (What does Thurston’s new construction in marshland really cost?)

  • Precious natural places are destroyed despite opposition of neighborhoods (e.g. Thurston and Lawton Elementary Schools).

  • A new school building is constructed on marsh and wetlands over unstable watersheds (Thurston, where 1143 neighbors signed a petition to save the Thurston Nature Center, and a group of neighbors (LetThurstonPlay.com) developed a new and better construction plan).

  • The AAPS Environmental and Sustainability Advisory Committee, promoted as part of the bond proposal, did not meet and has not reviewed the plan for Thurston Elementary School and the Thurston Nature Center.

  • There is no plan for the restoration, upkeep and stewardship of the Thurston Nature Center, which – while belonging to PTO, is cared for by volunteers and neighbors through fundraising and manual labor.

  • The AAPS board members pretend towards the media that they follow up on promises and that everybody who criticizes them is just ill informed. One example of many makes it easy to understand why especially the Thurston neighbors and supporters of the Thurston Nature Center do not trust the School Board: they also promised to save and support the care of the salamander population at Skyline High School - and then they didn’t. Read the heartbreaking story about the once vital salamander habitat, written by two high school students: Skyline’s Lost Salamanders: The Forgotten Wetlands and The Fight for Restoration.

  • New schools promised in the bond proposal will not be build (e.g. a fourth elementary school and a Pre-K and Young 5s school in NE Ann Arbor).

  • Children will not be staged during construction but are expected to learn mere feet from major construction zones (at Thurston, this poses a special problem for children with sensory sensibility issues, ADHD, etc.)

  • Elementary Schools will not have permanent stages. 50 art teachers have sent a public letter to protest and a petition from teachers and parents had garnered 1,247 signatures by June 16, 2025. Mobile stages have many ADA compliance issues. AAPS board members promised a meeting with music and theater teachers to discuss the stages in summer 2025. By January 2026, the meeting has still not been scheduled.

  • The promised cooperation with neighbors, parents and teachers did not happen, instead Gilbane facilitated information meetings (one per school in the NE of Ann Arbor), telling communities what would happen.

  • Neighbors attending earlier board meetings assert that the BOE Chair boasted the construction company her nephew is affiliated with (Christman Construction in Livonia, MI) will be a subcontractor for Thurston before bids were even requested.

  • Several neighbors assert that, at a meeting, the BOE President acknowledged that Gilbane Construction is lying about feasibility of Thurston Elementary construction but wouldn’t hold them accountable.

  • Gilbane, who is regularly hired to build in Michigan, has a history of losing lawsuits (bribery charges and not paying subcontractors). There is also a story about how Gilbane tried to take advantage of Lincoln High School in North Providence.

  • At Thurston, leading up to the meeting announcing the new plan, suddenly misinformation became an issue: two hoaxes where peddled to the neighbors - one was about rats in the old building and the other one about a completely broken plumbing system. Both claims could never be proven (yes, there might have been a rat at the garbage containers, and yes, one toilet was clogged), but it is interesting to see that now the school will be built right next to a natural rat habitat and next to trees with long roots on marshland, where roots can enter the sewer system much easier).

Letter to Board of Education, October 2024

Dear AAPS board members,

When Ann Arbor taxpayers were asked for a $1 billion bond program to improve the Ann Arbor Schools infrastructure, the program was framed around teaching and learning, and around “sustainable and environmentally responsible infrastructure.”

The Bond Phase plan for the first ten years (2020 to 2030) for the three Northeast schools, published online several years ago, showed the following:

Logan: construction 2025 to 2026 with staging

King: 2026 to 2027 with staging

Thurston: 2027 to 2028 with staging

Since then, as a community member living only 600 feet from Thurston school for nearly 30 years, I did not receive any new information about the construction of Thurston School, even though I searched online regularly. This summer we found out through the grapevine that Thurston construction would already begin in 2025. At a public meeting at Thurston School on September 26, we were officially informed that not only would Thurston be built two years earlier, but that staging was not considered and that a new school would be constructed on the Northern edge of the school property, directly adjacent to the Thurston Nature Center with the current structure becoming mostly asphalt and concrete.

I am very concerned about this plan and would like to add my remarks to the discussion hoping for further public discussions. While we all understand that there will be changes and that parts of the environment and neighborhood will be impacted, I am sure there must be a better way to reach the goal we all have: giving our children and teachers a proper and modern school while preserving our neighborhood and environment with the well-loved and well-cared for Thurston Nature Center. As mentioned many times, the Thurston Nature Center was the first of its kind in the United States and has been maintained by volunteers for well over five decades for the benefit of the children and for us all. Just replacing the existing school building at its place on a bigger footprint will already impact the environment around it, and we were aware of that.

Education though is more than just a modern school building:

There is the boy who is greeted by “his friend, the bull frog” every morning on his way to school.

There is the toddler laughing delightfully when a group of geese lands on the pond.

There is the five-year-old crossing paths with a snapping turtle laying her eggs.

There is the group of kids watching in awe when an egret catches and eats a fish.

There are the two girls standing absolutely still waiting to see who moves first: they or the great blue heron?

There are the neighborhood kids excited to see Monarch butterflies in their backyards due to the waystation that just celebrated its tenth anniversary.

All these experiences are part of a well-rounded upbringing. What better way to teach children to respect and enjoy nature than close to an elementary school in the middle of a neighborhood where children pass by every day?

We live in a town where election proposals to raise taxes in order to build a bigger green belt, to maintain our parks and to build more bicycle lanes easily get a majority vote every time. We all value nature and unspoiled environments as part of our urban surroundings. One of the reasons Ann Arbor is consistently voted as one of the best cities to live in is because of its pride in caring about the environment.

· the idea of a new building built next to the iconic nature center on what now is grass and a butterfly and hummingbird garden

· the idea of the space now occupied by a building and parking lot becoming an even bigger parking lot and street, with hardly any green space left

· the idea that instead of the oak savanna and rain garden we will have rain swales (which for safety reasons need to be fenced in, therefore impacting the visual pleasure of nature)

· the idea that water runoffs from the construction site will run into the Nature Center and eventually into the pond

· the idea of the new, partly two-story tall building overshadowing a part of the woods, changing the ecosystem forever (since it would be located right on the southern edge of the Nature Center)

· the idea of a community plaza built between the building and the woods inviting trash and trampling of groundcover

· the idea of daily noise and light pollution chasing away shy animals for good

… all this is just unfathomable to me.

Everybody knows that things can’t stay the same forever, but we also have learned that some things that were developed in the past were done for a reason and need to stay for the greater good of all.

Following through with the construction proposal introduced to us, the Thurston Nature Center would end up being an artificial green space like so many others; the pond would be devoid of most animals just like the small ponds along Plymouth Road between Prairie and Georgetown Blvd and on Commonwealth Blvd.

I cannot believe that most Thurston School parents would ignore all the environmental implications and learning opportunities to have the school built faster. I think staging at the new Logan School which is in the same neighborhood, not even half a mile away and right next to their kids’ future middle school, would not be a problem for most parents considering what is at stake. And I don’t believe that the Logan kids care if the Thurston kids being staged at Logan would be in the new school building first (stated as ‘unfair’ by the construction representatives). After all, the next 49 years any Logan pupil would also not have a new building anymore. Staging would not take 10 years as claimed in our community meeting. At the most, it would be six years for all three Northeast schools, and that would include three time-buffers of five months each, according to the construction timeline we were presented with.

I expect a construction company tasked with a project as big as the one they were hired for by Ann Arbor Schools to spend time learning about our city and its values. And I expect the local school board to adhere to the values of our community and our city. We all vote for AAPS board members, and for the tax raises supporting all kind of school projects; we entrust you to do right by our children, teachers and administrators but also to support our community's interests and our values.

When a project like the new Thurston School is finished as currently planned, the construction company moves on; the AAPS board members (who don’t seem to live in the neighborhood) leave the board and go back to their lives.

We, however, have to live with the irretrievable destruction of our space every day of every month of every year for ever.