Ann Arbor and the School Board (incl. Thurston Elementary School with its Nature Center)
General Timeline:
November 2019 (before the pandemic):
Ann Arbor votes for the $1 billion bond to renovate and build schools in the AAPS district. The proposal voted on noted the staging of schools. The MLive article reads that “Swift said the district would plan on building two "staging schools that would serve as a place for schools to move when their buildings are being renovated.”
The proposal was also framed around “sustainable and environmentally responsible infrastructure.”
December 2020:
The subsequent construction plan is published, showing the timelines for building, re-building and renovating all schools in the Ann Arbor Public School District, including building two new schools in NE Ann Arbor, one consolidating Pre K and Young 5s, the other one being an additional elementary school and staging location for other schools.
2021:
A plan to appoint a Bond Advisory Group is laid out.
July 2021:
Bernerd Rice is promoted to Executive Director of Physical Properties. After nearly 37 years at Garden City Public Schools; he came to AAPS in January 2018, the year before the $1 Billion Bond vote.
March 9, 2022:
AAPS announces applications for becoming a member of the Bond Advisory Group.
May 9, 2022:
Four Bond Advisory Group members are announced. Glenn L. Nelson is appointed as chair and confirms later that the group never met. From an MLive article on December 24, 2024:
“It’s been roughly three years since Ann Arbor Public Schools created an advisory group to help guide it through its lengthy list of school construction projects associated with its $1-billion capital bond.”
I think it would be beneficial to have the advisory committee,” said Stephanie Corona, a Gilbane Building Co. project executive who works with the AAPS capital bond team. “We were disappointed when it died on the vine.”
July 5, 2022:
AAPS purchases two properties. One is in the Domino’s Farms office park in Ann Arbor Township ($17 Million for a large office building on 16 acres, the area is only zoned for office buildings at this time), the other one north of Arborland Mall.
Quote from then Superintendent Jeanice Swift: “The purchase provides land and property for another school building and expansion of the district’s early childhood education programming… We feel that the Domino’s Farms location will be extremely convenient for many families, and by removing the preschool and young five, (students) potentially from our four north elementary schools, it will open up classrooms and allow us to accommodate the coming growth from housing development in that part of the city.”
July 2022:
Bernerd Rice is promoted to Assistant Superintendent Capital Program and Physical Properties.
November 18, 2022:
Samples for a Wetland Delineation at the Thurston Nature Center are quietly taken by OHM (Livonia, MI) on behalf of AAPS. (See photo on report: the ground is frozen and there is a layer of snow, and see December 8 and 12, 2022)
December 8, 2022:
The report of the Wetland Delineation at the Thurston Nature Center is completed and sent to AAPS.
December 12, 2022:
MLive announces that the next AAPS board meeting (December 14) is taking place at the newly purchased office building at Domino’s Farms office park:
“With a need for a new school in northeast Ann Arbor to relieve enrollment pressure at King Elementary School, Logan Elementary School, A2 STEAM School and Thurston Elementary School in the coming years, Swift previously noted the two-story office building is “ideal” to be designed into a preschool or early childhood center location.” (see December 8 -wetland delineation at Thurston already done - and see January 4, 2023)
“We are grateful for the support of our AAPS community, the bond committee trustees and the full board in supporting the work to acquire a property in the northeast sector of town,” Swift said. “The northeast sector is one of the parts of our town that has really critical long term need for additional space for district use.”
“The property is one of two approved by the district, totaling approximately 68 acres and costing AAPS $30.5 million.”
January 4, 2023:
AAPS decides to step away from the purchase of land near Arborland Mall for the new school they had promised to build for the northeast part of town.
“AAPS is no longer considering purchasing 52 acres of vacant land north of the Arborland shopping center that the Ann Arbor School Board approved purchasing in June, AAPS Spokesman Andrew Cluley said, while not commenting on the rationale for not moving forward with the purchase.”
March 8, 2023:
AAPS meets with teachers for the first time, asking only for input on the interior of buildings.
Until now (early 2026):
No changes have been made to the Domino’s Farms office building. It is only used for administration staff, who mostly work from home. Driving by there on different days and during different times shows nearly empty parking lots around the building. The plan for the promised preschool or early childhood center has been abandoned, as has the additional elementary school originally planned for the Arborland Mall location.
None of the changes, or explanations for the changes have been shared with the public.
Notes:
· AAPS Superintendent Jeanice Swift resigned on September 21, 2023.
· Jazz Parks was named interim Superintendent in October 2023. In March 2024, the school board abandoned its search process for the next district’s superintendent and offered Parks a permanent position as Superintendent with a 4 to 3 vote.
· AAPS Environmental and Sustainability Advisory Committee: The proposed committee was implemented and promoted as part of the bond proposal. The Mission statement says: “The Environment & Sustainability Advisory Committee will work with the Executive Director of Physical Properties to make recommendations in the development of an AAPS Environmental Sustainability Plan, including consideration of all the impacts of district decisions over the short and long term.” (see pages 18 to 21) The committee had not met in over a year and the plan for the Thurston neighborhood has not been reviewed.
Specifically to Thurston Elementary School and Thurston Nature Center:
Thurston Elementary hosts the only Preschool program on the Northeast side of the school district. The purchase of the office building at Domino’s Farms office park was supposed to house the new Pre K and Young 5s, the Arborland Mall property was supposed to become a new elementary school. This was planned to relieving pressure from the three elementary schools in the area -King, Logan and Thurston- and offer staging for the other schools while they are being renovated. The plan and timeline were still on the AAPS website (a2schoolsbond.org) on January 30, 2025:
However, things took an unexpected turn:
On September 26, 2024, the first and only community meeting at Thurston for the Thurston neighborhood took place in the evening. It was facilitated by Gilbane Construction, and it was not a good meeting: Gilbane representatives introduced a new construction plan showing Thurston would be rebuild completely starting in March 2025. To make matters worse, it would be built on wetlands encroaching on the southern part of the Thurston Nature Center, mere feet from the existing building, while regular school continues as usual. The timeframe would be two years for building the new school and two years for demolition of the old school including paving over the baseball diamond and the soccer fields, building over the raingardens, berms and oak savannah – all this in a neighborhood built over the instable Millers Creek watershed and prone to flooding. Neighbors were visibly shocked and upset and the Q&A session was very contentious. When neighbors and parents asked for plan revisions and changes, Gilbane representatives blocked and ended the meeting saying their clients were the AAPS board and not parents or community. Neighbors noticed that the plan must have been made with engineers or architects only looking at google maps: the one change to the plan Gilbane had presented was the location of the fire lane which was originally planned too close to Thurston Pond, in violation of environmental law.
Neighbors, including architects, forensic engineers, parents and others got together and created a group called Let Thurston Play. A petition to save the Thurston Nature Center garnered 1143 signatures, and the neighborhood group designed a plan to rebuild Thurston according to current school building codes, while saving the Thurston Nature Center and keeping students safe by staging during construction. All winter, in board meeting after board meeting, neighbors asked to halt construction and find a way for AAPS and Gilbane to work with the neighborhood. Hundreds of public commentaries were given at every meeting, sometimes neighbors only had 25 seconds each to voice their concerns, because so many wanted to speak. On the ‘other’ side, only a handful of neighbors didn’t mind the new plan, but barely voicing their support.
On February 25, 2025, the night before the vote on the Thuston construction, the neighbors from ‘Let Thurston Play’ were given a short time to present their plan, however, without any Q&A or discussion. Representatives from the Thurston Nature Center were not allowed to speak at all. By this time, U.S. Rep. Debbie Dingell, State Sen. Sue Shink, State Rep. Jennifer Conlin, Washtenaw County Commissioner Andy LeBarre and representations of the Huron River Watershed Council had all sent public letters, asking AAPS to reconsider their plans for Thurston. (Letters are on the Thurston Nature Center website)
One day later, on February 26, after neighbors one more time voiced their concerns and pleaded for reconsideration, the AAPS school board voted 4 to 3 to go ahead with the new Thurston plan.
On March 25, 2025, the long-established oak savannah was razed. Volunteers moved plants from the rain garden and the monarch butterfly way station which was destroyed in mid-June. Many trees were cut down when construction began on June 12, 2025.
The South Prairie, first designed in 1988 by Professor Bob Grese, director of the Matthaei Botanical Gardens and Nichols Arboretum at UM, is now the entrance for the new street bringing in construction equipment and will later serve as the fire lane. The land belongs to the city of Ann Arbor and has been a designated native prairie with endangered plants onside. AAPS has secretly been trying to buy this piece of land and allow for its designation to be changed so they can pave over the prairie (in paperwork FOIA-ed by neighbors). Documentation has misrepresented habitats for plants. In addition, the proposed street is above the Millers Creek watershed, not even three feet from a culvert where you can hear the water rushing below ground at all times and not even ten feet from an extensive and growing vernal pool, highlighting the unstable ground conditions.
Where does all this leave us? The impact of this ill-prepared plan is manyfold, environment, children and neighbors will suffer. Gilbane, which has a long history of being sued, and AAPS have – against their promise – not engaged with the community nor listened to the vast majority of neighbors but instead omitted information and actively disinformed the community. Some AAPS board members are bullying anybody who opposes their plan. There is also video of AAPS Chair Baskett’s companion repeatedly heckling the chair of the Thurston Nature Center during Q&A at a townhall meeting with U.S. Rep. Debbie Dingell and others. ‘Let Thurston Play’ wanted to poll Thurston teachers to find out how they felt about the changes and had to resort to an online questionnaire with the possibility for teachers to answer anonymously, because many teachers feared repercussions if speaking openly.
As of January 2026:
There is no update on money spent and no running budget on the district wide school construction
The Advisory Committee is still without members and therefore has never met
AAPS board members and Gilbane Construction have still not met with the district’s music and theatre teachers after teachers and parents voiced concerns earlier in 2025 when they found out that none of the elementary schools will have a permanent stage and/or auditorium
There is no plan on how to establish stewardship for the Thurston Nature Center. While part of Thurston PTO, neighbors and volunteers keep up the area and ask for donations in money and labor. The environmental fall-out will has not been addressed
As of summer 2026:
It has been announced that AAPS is over budget concerning the construction and rebuilding of all schools. There is talk about closing a couple of schools completely and about selling the administration building on Earhart Road. As a reminder: this is a $1 Billion bond plus several sinking taxes, totaling about $1.5 Billion, only for construction and renovations.
As of fall 2026:
The chair, vice chair and president of the AAPS Board of Education were up for re-election this fall and neither ran again. All three voted for the new plan the rebuild Thurston in its new location adjacent to the Nature Center (in addition to one more board member). For most of the time since 2019, Chair and Vice Chair were the only members overseeing the $ 1 Billion bond voted for by Ann Arbor tax payers.